Service alerts

Construction, utility, service, and other facility-related alerts featured on this page are also emailed to all relevant faculty and staff listservs. Manage your building notice subscription(s) on our building notifications page.

Please note that Facilities Services has regularly scheduled power disruptions that are not listed on this page.


The following facilities have active service alerts:

  • Anderson Health Science (AHS)

    Construction notice


    Affected dates

    Thursday, September 8, 2022, through Friday, January 20, 2023

    Description of work

    • Contractors will upgrade the fire alarm systems.

    Impact for Occupants:

    • There will be intermittent noise, dust, vibrations, and non-toxic odors associated with this project.
    • There will be intermittent detours within the building

    Action(s) Required:

    • Please use caution near construction equipment and crews.
    • Please do not enter sealed-off construction areas.
  • Sarah H. Fleischmann Building

    Construction notice


    Affected dates

    Monday, November 14, 2022, through Friday, November 25, 2022

    Description of work

    A certified contractor will remove asbestos-containing flooring from suite 100. Our Environmental Health and Safety department staff will be on-site to conduct air monitoring to confirm there is no release of asbestos because of this work.

    Impact for Occupants

    • Rooms 100C through 100H will be inaccessible for the duration of the project
    • There may be intermittent noise, dust, vibrations and non-toxic odors associated with this project

    Actions(s) Required

    • Please use caution near construction equipment and crews
    • Please do not enter sealed-off construction areas
  • Howard Medical Sciences (HMS)

    Construction notice


    Affected dates

    Thursday, September 8, 2022, through Friday, January 20, 2023

    Description of work

    • Contractors will upgrade the fire alarm systems.

    Impact for Occupants:

    • There will be intermittent noise, dust, vibrations, and non-toxic odors associated with this project.
    • There will be intermittent detours within the building

    Action(s) Required:

    • Please use caution near construction equipment and crews.
    • Please do not enter sealed-off construction areas.
  • Lombardi Recreation Center (LRC)

    Construction notice


    Affected dates

    Monday, November 28 through Friday, December 23, 2022

    Description of work

    A contractor will excavate a trench for an electrical utility upgrade. The work will occur in the parking lot immediately south of the Lombardi Recreation Center.

    Impact for occupants

    • There will be intermittent vehicle and pedestrian detours.

    • There will be intermittent noise and non-toxic odors associated with this project.

    Action(s) required

    • Please use caution when near any construction activity or equipment.

    • Stay out of coned-off and barricaded construction areas.

  • Manville Health Science (MHS)

    Construction notice


    Affected dates

    Thursday, September 8, 2022, through Friday, January 20, 2023

    Description of work

    • Contractors will upgrade the fire alarm systems.

    Impact for Occupants:

    • There will be intermittent noise, dust, vibrations, and non-toxic odors associated with this project.
    • There will be intermittent detours within the building

    Action(s) Required:

    • Please use caution near construction equipment and crews.
    • Please do not enter sealed-off construction areas.
  • Nellor Biomedical Sciences (NBS)

    Construction notice


    Affected dates

    Thursday, September 8, 2022, through Friday, January 20, 2023

    Description of work

    • Contractors will upgrade the fire alarm systems.

    Impact for Occupants:

    • There will be intermittent noise, dust, vibrations, and non-toxic odors associated with this project.
    • There will be intermittent detours within the building

    Action(s) Required:

    • Please use caution near construction equipment and crews.
    • Please do not enter sealed-off construction areas.
  • Savitt Medical Science (SMS)

    Construction notice


    Affected dates

    Thursday, September 8, 2022, through Friday, January 20, 2023

    Description of work

    • Contractors will upgrade the fire alarm systems.

    Impact for Occupants:

    • There will be intermittent noise, dust, vibrations, and non-toxic odors associated with this project.
    • There will be intermittent detours within the building

    Action(s) Required:

    • Please use caution near construction equipment and crews.