The following general procedures and divisions of responsibility shall govern the capital improvement programming of university projects:

  1. The University shall determine the sequence of priority and scope of work of all university projects.
  2. The sequence of priority and scope of work shall be submitted to the Nevada System of Higher Education and the State Public Works for review and comment.
  3. The State Public Works shall develop budget estimates of total project costs based on the project scope of work and shall submit the budget estimates to the University for review prior to adoption.
  4. The State Public Works shall have the responsibility for assigning the priority of university projects in the statewide program and, in doing so, agrees not to modify the sequence of priority established by the Regents for university projects.