Preproduction Schedule
EIR
2.5 years Jan 2000- Jul2002
Permitting/Plan of Operation
1 year 2002
Surface Facilities
1.5 years Aug 2002 - Dec 2003
Contracted mine work
4 months Sep 2003- Dec 2003
Mine Start up
January 2004