PPT Slide
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2001 2002 2003 2004 2005 2006 2007
Permitting
Baseline Study/EIS
Access Rd.
Power Line
Haul Roads
Pre-Strip
Underground
Buildings
Processing Fac.
Misc. Develop.
Start Mining
Pour Dore’
Pre-Production Schedule
Pre-Production
Mining
Q1 Q2 Q3 Q4