Mining: Pre-Production
Baseline Study: 1 year, $1 million
Permitting: 1 year, $1.15 million
Construction Period: 2 years, $37.6 million
- Includes:
- Road Construction: $426,600
- Building Site Preparation: $7,018
- Power Line: $500,000
- Tailings Dam: $36.6 million