SUMMARY
LOCATION LANDER COUNTY, NEVADA
PROJECT OPEN PIT GOLD MINE
MINE LIFE .10 YEARS
ANNUAL PRODUCTION .. ..4.8 MILLION TONS OF ORE
283,500 OUNCES OF GOLD
STRIPPING RATIO 2.5:1
PROCESS HEAP LEACHING
RECOVERY 74%
PROJECT COST .$73.2 MILLION
BANK LOAN .$36.6 MILLION AT 6% OF INTEREST
PRESENT VALUE .$10.8 MILLION
INTERNAL RATE OF RETURN ..24%
CASH COST PER OUNCE $165