SUMMARY OF PROJECT
Project is Feasible
- Rate of Return: 31.8%
- Net Present Value of $11.5 Million
- Based upon Hurdle Rate of 15%
-
R.O.M. Production Summary
- 27.3 Million Tons Mined
- Average BTU: 11970
- Average Sulfur: 0.47 wt. Percent
- Average Ash: 7.84 wt. Percent