ORE PROCESSING
ORE PER DAY = 14,600tons
PRIMARY CRUSHER = 6in
SECONDARY CRUSHER = 3/4in
LEACH PAD
46.8 MILLION TONS OF ORE
RECOVERY = 74%
FOOT PRINT 7 MILLION FT2
SIX 25ft LIFTS
SLOPE = 1:1.5
45 DAY CYCLE
654,500 TONS PER CYCLE
RECONTOURED SLOPE = 1:3